Powered by: Motilal Oswal
01-01-1970 12:00 AM | Source: IANS
Coal Ministry offers relaxation in Revision of Performance Bank Guarantee
News By Tags | #1425 #2678 #813 #612 #845

Follow us Now on Telegram ! Get daily 10 - 12 important updates on Business, Finance and Investment. Join our Telegram Channel

Coal Ministry Offered relaxation in Revision of Performance Bank Guarantee and extended Bid due date for Commercial Coal Block auction upto January 30.

The Ministry of Coal had launched the sixth round and second attempt of fifth round of commercial coal mines' auction on November 3, 2022 for 141 coal mines. Considering the demand from the industry and to promote Ease of Doing Business (EoDB), the Ministry has decided that going forward the first revision in the Performance Bank Guarantee (PBG) would be done upon grant of mine opening permission for the respective coal mines.

As per the provisions of the tender document, the Performance Bank Guarantee (PBG) to be submitted for each successfully auctioned coal mine is to be revised annually based on the National Coal Index (NCI) for the month of April in the beginning of the year. Since NCI has become double since the launch of first commercial coal mine auctions in 2020, several representations were received from the industry for relaxation in PBG revision provisions.

It was requested that unprecedented increase in NCI has led to significant financial burden on successful bidders, whose mines are in the pre-operationalisation stage, impacting fund availability for mine operationalisation activities, said officials.

Officials said that this initiative is expected to reduce the financial burden on the bidders during the process of operationalisation of the coal mines and is expected to enhance participation from the bidders in the commercial coal mines' auctions. In lieu of the same and to effectuate this amendment in the ongoing round of auction, the Ministry has extended the auction bid due date to January 30, 2023 from its earlier bid due date of January 13.