01-01-1970 12:00 AM | Source: Accord Fintech
335 infrastructure projects show cost overruns of Rs 4.46 lakh crore: MoSPI
News By Tags | #248 #612 #309

Follow us Now on Telegram ! Get daily 10 - 12 important updates on Business, Finance and Investment. Join our Telegram Channel

https://t.me/InvestmentGuruIndiacom

Download Telegram App before Joining the Channel

The Ministry of Statistics and Programme Implementation (MoSPI) in its report for January 2023 has said that as many as 335 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.46 lakh crore. According to the Ministry, which monitors infrastructure projects worth Rs 150 crore and above, out of 1,454 projects, 335 reported cost overruns and as many as 871 projects were delayed.

It mentioned that total original cost of implementation of the 1,454 projects was Rs 20,59,065.57 crore and their anticipated completion cost is likely to be Rs 25,05,248.43 crore, which reflects overall cost overruns of Rs 4,46,182.86 crore (21.67 per cent of original cost). The expenditure incurred on these projects till January 2023 was Rs 13,53,875.70 crore, which is 54.04 per cent of the anticipated cost of the projects.

However, it said the number of delayed projects decreased to 703 if delay is calculated on the basis of the latest schedule of completion. Further, it showed that for 309 projects neither the year of commissioning nor the tentative gestation period has been reported. Besides, it said  out of the 871 delayed projects, 169 have overall delays in the range of 1-12 months, 157 have been delayed for 13-24 months, 414 projects for 25-60 months and 131 projects have been delayed for more than 60 months. The average time overrun in these 871 delayed projects was 39.69 months.