Powered by: Motilal Oswal
01-01-1970 12:00 AM | Source: Accord Fintech
Around 438 infrastructure projects show cost overrun of Rs 4.34 lakh crore
News By Tags | #5804 #248

Follow us Now on Telegram ! Get daily 10 - 12 important updates on Business, Finance and Investment. Join our Telegram Channel

The Ministry of Statistics and Programme Implementation in its report has said that as many as 438 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.34 lakh crore. Total original cost of implementation of the 1,680 projects was Rs 21,74,182.86 crore and their anticipated completion cost is likely to be Rs 26,08,330.02 crore, which reflects overall cost overruns of Rs 4,34,147.16 crore (19.97 per cent of original cost). 

According to the report, the expenditure incurred on these projects till October 2021 is Rs 12,64,545.31 crore, which is 48.48 per cent of the anticipated cost of the projects. However, it said that the number of delayed projects decreases to 377 if delay is calculated on the basis of the latest schedule of completion. Further, for 837 projects neither the year of commissioning nor the tentative gestation period has been reported. It pointed out that reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems are among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 as a reason for the delay in implementation of these projects. It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.